2025

Vanak office tower

Nine floors of Cat 6A horizontal cabling with a 12-core OS2 backbone between floor racks. The building stayed occupied throughout, so work ran floor by floor and partly outside office hours. All 1,200 ports were permanent-link tested and reports issued per floor.

2024

Alborz industrial plant

Six production halls linked by a 2.4 km single-mode fibre backbone. Distance and electromagnetic noise ruled out copper from the start. Power budget was calculated before installation; worst-path loss measured 0.9 dB against a comfortable design margin.

2024

Central hospital

640 ports delivered in seven phases inside active wards. Temporary parallel paths kept critical systems online during each phase, and physical work ran on night shifts. LSZH cable throughout, per healthcare fire requirements.